Work packages
Five work packages across a 24-month project.
- WP1
Network and community engagement
24 months · phases: months 1–6, 7–12, 13–18, 19–24
- WP2
Platform development
Months 7–24 · 18 months · full public launch in months 19–24
- WP3
FAIR-enabled fungal research data
Timeline to be confirmed
- WP4
FAIR-enabled fungal research software
Timeline to be confirmed
- WP5
Digital competency training programme
Timeline to be confirmed
Planned deliverables
- Curated metadata and genomic data from about 10–15 institutional partners
- A public web portal
- A fungal knowledge graph
- Training courses